-
Initial Consultation (Week 1):
Contractor visits site, discusses your checklist answers, asks clarifying questions to understand vision and priorities. Takes measurements and photos, assesses site conditions (slope, drainage, access, obstacles). Discusses material options, preliminary design ideas, realistic budget ranges. Good contractors listen more than talk during this phase.
Duration: 1-2 hour site visit. Your prep: Complete checklist beforehand, have photos ready, be ready to discuss must-haves vs nice-to-haves.
-
Concept and Design Development (Week 1-2):
Contractor prepares design drawings showing layout, elevations, material selections. May include 3D renderings or visualization tools to confirm vision alignment. Reviews design with you, makes adjustments based on feedback. Finalizes dimensions, materials, features, ensuring design meets your functional needs and budget.
Duration: 3-7 days from consultation to design presentation. Your role: Provide feedback promptly, make material selections, approve final design before proposal preparation.
-
Detailed Proposal Preparation (Week 2-3):
Contractor prepares written bid covering complete scope, materials specifications, timeline, payment terms, warranties. Includes drawings/renderings, material samples if applicable. Professional proposals are 5-15 pages with line-item breakdowns, not one-page estimates. Review carefully against your checklist and other bids—this is your contract foundation.
Duration: 2-5 days from design approval to proposal delivery. Your role: Review thoroughly, ask clarifying questions, compare with other bids, negotiate if needed, make decision.
-
Contract Signing and Permitting (Week 3-4):
Once you sign contract and pay deposit (typically 10-30%), contractor begins permit process. Files applications with local building department, provides structural drawings if required, pays permit fees (unless contract specifies homeowner pays). Permit processing time varies by municipality—2-6 weeks typical in Chicago suburbs.
Duration: 2-6 weeks depending on jurisdiction. Your role: Sign contracts promptly, pay deposit, provide any homeowner signatures needed for permit application, be patient during processing.
-
Material Ordering (Week 4-6, concurrent with permitting):
Contractor orders materials based on finalized design. Lead times vary: stock materials ship in 1-2 weeks, custom colors or special orders take 3-6 weeks. Spring/summer peak season adds time. Contractor coordinates delivery timing with construction schedule start date. Materials typically delivered just before construction begins to avoid weather damage during storage.
Duration: 1-6 weeks depending on materials. Your role: Finalize all material selections early, respond quickly to any contractor questions, be flexible if first-choice materials have long lead times.
-
Pre-Construction Meeting (Week before construction):
Final walkthrough of plans, material confirmations, site logistics review (equipment access, material storage, work hours). Timeline review with milestone dates. Contact protocols during build (daily updates, who to call with questions). Establish homeowner presence requirements (when you must be available for decisions). Confirm payment schedule and change order process one final time.
Duration: 30-60 minute meeting/call. Your role: Clear your schedule for construction dates, prepare property (move patio furniture, pets secured), provide contractor with any needed access (gate codes, contact info if you'll be away).
-
Construction Phase (Variable, 1-3 weeks typical):
Day 1-2: Site prep and excavation. Layout deck footprint with string lines, mark footing locations, call JULIE to re-verify utilities, excavate footing holes to proper depth (42" Chicago area).
Day 2-3: Footings and posts. Pour concrete footings, set post anchors or posts, allow concrete to cure (24-48 hours). First inspection point for many jurisdictions.
Day 3-5: Framing. Install ledger board with proper flashing, set beams and joists, install joist tape. Framing inspection before proceeding to decking.
Day 5-8: Decking installation. Install deck boards using specified fastening system, proper spacing, stagger joints for appearance and stability.
Day 8-10: Railings and stairs. Install railing posts, top/bottom rails, balusters or infill panels. Build stairs with proper rise/run, install handrails.
Day 10-12: Features and finishing. Install lighting fixtures and electrical (final electrical inspection), built-in seating/planters, any shade structures. Final cleanup, debris removal.
Duration: 5-15 working days depending on size/complexity. Weather adds time. Your role: Be available for questions, keep pets/children away from work area, make space for material delivery/storage, respond promptly to any contractor communications.
-
Final Walkthrough and Completion (Last day of construction):
Contractor walks through completed work with you, demonstrates features (if lighting, show controls), points out any care requirements. You create punch-list of any items needing attention (small touchups, minor adjustments). Contractor addresses punch-list items immediately or schedules return. Provides care and maintenance instructions, warranty documentation, any product manuals (lighting, electrical). Collects final payment upon your approval. Requests review/referral if you're satisfied.
Duration: 30-60 minute walkthrough. Your role: Inspect thoroughly, test features, create complete punch-list during walkthrough (not days later), ask questions about care/maintenance, make final payment, leave review if satisfied.